1
00:00:00,000 --> 00:00:08,000
Alan Cring Productions in association with Emergent Light Studio presents

2
00:00:10,000 --> 00:00:16,240
the Illinois State Collegiate Compendium Academic Lectures in Business and Economics.

3
00:00:17,840 --> 00:00:24,080
This is Business Finance, FIL 341 for Autumn Semester 2024.

4
00:00:24,080 --> 00:00:37,840
Today, problems in capital budgeting. The basic outline is pretty much anything that you would

5
00:00:37,840 --> 00:00:44,000
need to do is in the spreadsheet that I am providing for you. Although I do want to make

6
00:00:44,000 --> 00:00:51,280
some comments on proceeding forward with the capital budgeting, how you use some of the back

7
00:00:51,280 --> 00:00:58,720
sheets to answer a few questions. And this is just some stupid Excel pet tricks. As a matter of fact,

8
00:00:58,720 --> 00:01:06,480
I came in a few minutes late because I just realized that I could actually write a worksheet

9
00:01:06,480 --> 00:01:14,000
in there to calculate payback period. So that's in your portfolio now too. But before we go any

10
00:01:14,000 --> 00:01:19,520
further here, just a quick look at the numbers to see how the markets are doing. And you have a

11
00:01:19,520 --> 00:01:27,120
day a slide day here. Well that's not very helpful. Wait, let me see something here. Let's try that

12
00:01:27,120 --> 00:01:37,600
again. Oh there we go. Okay, well, huh, that's odd. Okay, well anyway, one way or the other.

13
00:01:38,560 --> 00:01:46,320
As you can see, it's a sour day on the street. It's nothing major, but there is a, the Dow

14
00:01:46,320 --> 00:01:54,080
is down the most today. And a lot of that's probably price correction from the heady days

15
00:01:54,080 --> 00:02:04,160
of the last of this past week. The markets surged upward and now they, the profit takers are coming

16
00:02:04,160 --> 00:02:11,280
in and peeling off some of their equity holdings just to get some money out of them before something

17
00:02:11,280 --> 00:02:20,320
else happens. The thing that kind of creeps me out is there's this pervasive rumor and I've never

18
00:02:20,320 --> 00:02:26,080
heard, there's always doomsayers, you know, the end of the world is coming and all that, that's

19
00:02:26,880 --> 00:02:36,320
through time and history. And I've heard it on from traders all the time you hear one,

20
00:02:36,320 --> 00:02:43,440
well the market's about to crash, markets are ready for a big fall. I'm hearing it a lot more.

21
00:02:44,800 --> 00:02:51,200
The last few weeks there was kind of a pickup in it, but just this last couple of days it's there,

22
00:02:51,200 --> 00:02:59,200
it's almost like noise of the sense that any time now the markets, the bottom is just going to drop

23
00:02:59,200 --> 00:03:06,160
out from the market. And I don't, how much do you believe it? Well, I don't, but at the same time

24
00:03:06,160 --> 00:03:13,440
it's just almost like, it's assumed now that it's coming. But of course you don't see anyone

25
00:03:13,440 --> 00:03:21,040
panicking yet and you certainly don't see the gold markets responding too much, but it's just like an

26
00:03:21,040 --> 00:03:28,640
underlying hum that there's a black swan coming very soon. So well, does that mean you sell out

27
00:03:28,640 --> 00:03:34,720
today and go live in the woods? Certainly not. And it probably amounts to nothing. Like I said,

28
00:03:34,720 --> 00:03:40,800
you hear these rumors all the time. It's just that the noise of it is getting kind of annoying right

29
00:03:40,800 --> 00:03:47,600
now. Now as you can see crude is really in a trading band. You see that bouncing there, but

30
00:03:49,200 --> 00:03:56,080
that's not even a dollar of bounce up and down right now. And so it's a good time and you are

31
00:03:56,080 --> 00:04:02,880
beginning to see gasoline prices, more of them, just under three dollars a gallon. That's good

32
00:04:02,880 --> 00:04:09,440
news. So that's helpful going into the Christmas season. And right now we're all holding our breath.

33
00:04:10,400 --> 00:04:16,720
The preliminary numbers pre-black sale are weak and we're hoping that that just means that everyone's

34
00:04:16,720 --> 00:04:22,000
waiting for Black Friday and they're all going to buy their brains out. But we're just going to have

35
00:04:22,000 --> 00:04:29,600
to see if black, as I said in the last class, if Black Friday comes in weak, in other words not as

36
00:04:29,600 --> 00:04:35,040
good as last year, we're probably going to have a bad Christmas season and that's going to be bad

37
00:04:35,040 --> 00:04:40,960
for the economy. That's a bad message going into the new year. In other words, the Christmas season

38
00:04:40,960 --> 00:04:50,320
is a leading indicator of business activity for the year following. And so we want to keep an eye

39
00:04:50,320 --> 00:04:56,400
on that to see if it's going to be a good strong Black Friday or a bad Black Friday. The numbers

40
00:04:56,400 --> 00:05:03,920
should start coming in Saturday night, Sunday. We should start seeing what happened on Black Friday.

41
00:05:03,920 --> 00:05:10,560
So we keep an eye on that as finance people, those kinds of numbers. Now looking here at gold, as I

42
00:05:10,560 --> 00:05:17,520
said, gold is showing no apocalyptic behavior. If you start to see the gold price surge upward,

43
00:05:17,520 --> 00:05:25,120
especially if it crosses, even comes close to three thousand dollars an ounce, that is a warning sign,

44
00:05:25,120 --> 00:05:32,880
that's a real warning sign. Right now it's just sitting there looking stupid, $2,700, $2,600 an

45
00:05:32,880 --> 00:05:42,160
ounce, not moving much. So we're in good shape there. Coming over here, silver is behaving

46
00:05:42,160 --> 00:05:49,440
differently than from what gold is right now. That's not terrible, but it does indicate

47
00:05:49,440 --> 00:05:56,480
that the gold bugs are not in play right now. They're staying off the sidelines. But the

48
00:05:56,480 --> 00:06:02,560
10-year bond, now this is getting to be a little ridiculous here. The yield on the 10-year bond

49
00:06:02,560 --> 00:06:10,080
keeps going up, and that is going to stifle a recovery if it doesn't quit it. Because that

50
00:06:10,080 --> 00:06:20,800
10-year bond, if it gets back up, I mean, the concern, the first neckline that would really

51
00:06:20,800 --> 00:06:31,440
worry us is if it crosses back above 4.5 percent. Right now it's at 4.43 percent, and it's up about 12 basis points down.

52
00:06:31,440 --> 00:06:40,960
I probably haven't said this before. If you go one, two, even five basis, four basis points movement, either way,

53
00:06:42,080 --> 00:06:51,120
that's nothing. But once you get above four or five, about five, then that concerns us. And now we've got today,

54
00:06:51,120 --> 00:06:57,680
it's up a whopping 12 basis points, and that's not good at all. It's, unfortunately, as you can see,

55
00:06:57,680 --> 00:07:03,280
it's leveled off. We're coming to the end of the cycle, about four hours left on bonds today.

56
00:07:03,280 --> 00:07:11,280
And right now the sell-off has ended. You see that sell-off there? That's price going down,

57
00:07:11,280 --> 00:07:16,960
yield going up, the sell-off of the bonds. And interestingly enough, as you see over here,

58
00:07:16,960 --> 00:07:22,080
just having a quick look back over here at the equities, that sell-off in bonds was generating

59
00:07:22,080 --> 00:07:28,880
funds. Those funds are not going into equities. So that, and it's not going into gold either,

60
00:07:28,880 --> 00:07:37,440
so that's clearly going into liquidity. But remember when I said that a lot of this money

61
00:07:37,440 --> 00:07:43,520
isn't going into quick, high liquidity money markets, it's going into lower liquidity

62
00:07:43,520 --> 00:07:52,800
CDs, certificates of deposit, one to three year CDs. And so that's concerning. In other words,

63
00:07:52,800 --> 00:07:59,760
stashing money so that you can get to it if you have to, but it's stashed away for more than a day,

64
00:08:00,320 --> 00:08:06,640
10 days, and all that. So there's no plan, it doesn't look like the investors have a plan

65
00:08:06,640 --> 00:08:14,480
to bring those funds, those liquid funds, back onto the playground of equities in the near future.

66
00:08:14,480 --> 00:08:21,120
And that just keeps happening and more and more every day more CD activity is going on. Now the

67
00:08:21,120 --> 00:08:28,480
whole world of CDs sounds boring, but it's actually not that boring. I covered in 340, FIL 340, that

68
00:08:28,480 --> 00:08:35,520
there is an active certificates of deposit primary market, but also there's a secondary market for

69
00:08:35,520 --> 00:08:44,640
certificates of deposit. In other words, in this world, if you bought a CD from me, a substantial

70
00:08:44,640 --> 00:08:50,000
interest penalty for early withdrawal, so you're stuck with it for three years, right? You're not,

71
00:08:50,000 --> 00:08:55,920
because there's a secondary market. Someone else might want to buy your CD and there's a secondary

72
00:08:55,920 --> 00:09:02,160
market. So that whole interest penalty for early withdrawal really isn't all that meaningful

73
00:09:02,160 --> 00:09:08,000
anymore because of this highly active market. And there are brokers and there are also dealers in

74
00:09:08,000 --> 00:09:15,520
CDs on the secondary market side. In other words, a broker takes an order, finds a match for it over

75
00:09:15,520 --> 00:09:20,560
here. A dealer actually keeps an inventory of whatever security it is you're talking about.

76
00:09:20,560 --> 00:09:26,720
So there are brokers and dealers and it's a thick market and there's more participants every day.

77
00:09:26,720 --> 00:09:35,680
Traditional securities brokers are stepping into the world of CDs because there is a market for,

78
00:09:35,680 --> 00:09:40,080
there is an active secondary market. So there's money to be made, so they're jumping into this

79
00:09:40,080 --> 00:09:47,520
market. And so that's of some concern to us right now, that these CDs, first of all, they're gathered,

80
00:09:47,520 --> 00:09:53,360
the number of CDs is growing. That's primary market. And the activity of trading in the CDs,

81
00:09:53,360 --> 00:09:59,040
that's a secondary market, is picking up enough that you're having new players that used to do

82
00:09:59,040 --> 00:10:08,240
only traditional kinds of deals in stocks and bonds. Now they're jumping into this too. And so yeah.

83
00:10:08,240 --> 00:10:15,040
So like people going into the CDs, are they expecting the hailed savings accounts to be going down?

84
00:10:15,040 --> 00:10:22,640
Yeah, yeah. Very good. That's exactly right. Yeah, that's the idea. And that's the major one. There

85
00:10:22,640 --> 00:10:30,880
are other reasons, but that's a big one right there. Good point. And what this means is that

86
00:10:30,880 --> 00:10:38,640
there are a lot of flashes of danger ahead. And whether or not those are just some storm off in

87
00:10:38,640 --> 00:10:47,200
the distance or if it's coming at us, we can't say yet. But it isn't certainly a time of a lot of

88
00:10:47,200 --> 00:10:54,960
excitement. It is a time of a lot of excitement. The heading belief that what was the election was

89
00:10:54,960 --> 00:11:05,120
going to be the golden age of trading and finance, that's going away pretty quickly,

90
00:11:05,120 --> 00:11:13,040
because especially because of the concern about a global tariff war, which would put us back to 1929

91
00:11:13,040 --> 00:11:17,840
and what happened after that. That's a concern and it's beginning to build on Wall Street.

92
00:11:20,640 --> 00:11:26,480
But it's not a reason for trading out and getting out right now. It's certainly not at all.

93
00:11:27,040 --> 00:11:35,040
I don't want to give that an impression. Now the one thing though is that we do see the dollar

94
00:11:35,040 --> 00:11:42,560
sliding against other currencies. It's beginning to weaken and that's just how it is. You see

95
00:11:42,560 --> 00:11:47,840
just as a quick mention and if you want to get more, if you're interested in international finance,

96
00:11:48,560 --> 00:11:55,520
I teach it and we also have, Stella teaches it, and it's really interesting stuff. And the math

97
00:11:55,520 --> 00:12:03,680
isn't so bad. It's just you have to keep straight on what makes what happen. But the dollar is

98
00:12:04,320 --> 00:12:12,080
sliding against the euro, which is because of a belief that the strength of the American economy

99
00:12:12,080 --> 00:12:21,600
is not as great as it is against Europe. Now if you look over here and you check on the pound

100
00:12:21,600 --> 00:12:28,160
sterling, it's plummeting against the British pound. And the Japanese, it looks like it's going up,

101
00:12:28,160 --> 00:12:34,640
it's not. Their quotes are backwards because yen are of such small value compared to the dollar,

102
00:12:34,640 --> 00:12:41,440
they have to quote it backwards. So what you see going up, the dollar appreciating, is actually

103
00:12:41,440 --> 00:12:49,120
the dollar depreciating against the yen. If you look here, the yen is USD to yen. Over here,

104
00:12:49,120 --> 00:12:58,480
that's euro to USD and it's also Great Britain pound to USD. So this one's a backward quote.

105
00:12:59,520 --> 00:13:07,520
This is that one, the USD to Japanese yen is a direct quote because it's one dollar

106
00:13:07,520 --> 00:13:13,200
and the others are indirect. More likely you see indirect quotes for everything and you want to

107
00:13:13,200 --> 00:13:18,960
keep that it that way, but they have to quote it as a direct quote for the Japanese yen because

108
00:13:18,960 --> 00:13:33,280
it's worth so little. Look at this, 154.75, one dollar will buy you 154.75 yen. So if you turn

109
00:13:33,280 --> 00:13:38,320
that around, that would be in tiny decimal places if you turned it into an indirect quote.

110
00:13:38,880 --> 00:13:47,280
But anyway, that's that one going on. Now a few on the horizon. This is a cautionary tale. Let

111
00:13:47,280 --> 00:13:57,760
me show you just a couple of stocks and what it means of beta and its relationship to risk. One

112
00:13:57,760 --> 00:14:10,080
that I'll show you right now is Micron. Micron swings badly. It's not an amateur's kind of game.

113
00:14:10,080 --> 00:14:18,400
It's got a beta of 1.18. It's highly overvalued and if you want to look at this one for a one year,

114
00:14:18,400 --> 00:14:28,240
that is risk-rich-large. Look at that. It surges and falls and surges and falls. Now if you have the,

115
00:14:30,240 --> 00:14:37,440
if you do cardio and you have your heart doctor's permission, this is a stock that you might want to

116
00:14:37,440 --> 00:14:45,520
go with, but it's certainly not something that you are going to say, well I'm rich, now I can live the

117
00:14:45,520 --> 00:14:51,200
great life because tomorrow you might not be rich and you'll be living in a dumpster. And that's a

118
00:14:51,200 --> 00:15:00,720
good example of that. Another one which had a boost because of the belief that the owner's new

119
00:15:00,720 --> 00:15:09,280
government position will make him have more ability to leverage that on his company is Tesla. On one

120
00:15:09,280 --> 00:15:15,680
day it surges and the next day it just crashes. Going back here again, look at one year, and you

121
00:15:15,680 --> 00:15:22,640
will see the ups and downs and the spike and now correcting off the spike again. And of course the

122
00:15:22,640 --> 00:15:32,720
Tesla beta is insanely high and so if you're going to buy something like this, it's not one of those

123
00:15:32,720 --> 00:15:40,080
buy it and hold it for a week and make a fortune and then get out. If you're going to do a stock

124
00:15:40,080 --> 00:15:46,720
like this, this is just something you have to put in a drawer and walk away from and in 10 years you

125
00:15:46,720 --> 00:15:53,840
see where you are. That's one of the things about highly volatile stocks. Unless you think you're a

126
00:15:53,840 --> 00:16:00,880
genius at timing, they are not quickie investments at all. And I just want to bring those up to you

127
00:16:00,880 --> 00:16:06,320
as one of those last things that I can impart to you before you leave me and I never see you again

128
00:16:06,320 --> 00:16:11,120
because you all go to Wall Street and make a fortune and then forget about your old professor

129
00:16:11,120 --> 00:16:19,600
here. But anyway, enough of that. Let me get down to the lecture here. Now I've uploaded another new

130
00:16:19,600 --> 00:16:27,280
version of that worksheet. This is capital budgeting. Figure out whether saw courses, whether

131
00:16:27,280 --> 00:16:34,160
project or go or no go. Now let me go over here to view student and just to remind you of where you

132
00:16:34,160 --> 00:16:43,280
want to be in this is pretty straightforward. Files, go to your spreadsheets. I said go to your

133
00:16:43,280 --> 00:17:00,000
spreadsheets and you use the NPV and IRR spreadsheet. This should solve all of your... yes please.

134
00:17:00,000 --> 00:17:18,400
I had an example on here I forgot to get it. But this is good enough that it should get you through

135
00:17:18,400 --> 00:17:24,080
almost... oh I did not want that. Please don't, please don't. No, no, no. I want to download

136
00:17:24,080 --> 00:17:33,840
NPV and IRR. I thought I did and it didn't show up. Oh it is up. Okay. Oh okay. Good.

137
00:17:36,480 --> 00:17:42,640
This should get you through about any problem that you would need. Now I'm going to assume you already

138
00:17:42,640 --> 00:17:52,080
know NPV IRR, at least what it is. This is our go no go for finding project whether we're going

139
00:17:52,080 --> 00:17:58,880
to take on projects or not. And it all boils down to free cash flow. We project the free cash flow

140
00:17:58,880 --> 00:18:05,200
and I've shown you some of that in chapter 11, went through some of it. And we just lay out the

141
00:18:05,200 --> 00:18:13,680
free cash flows for a company and then from there we get a couple of metrics. Now I'm repeating some

142
00:18:13,680 --> 00:18:29,040
of what I've done before here but let me do it again. The three methods, and I'm just repeating

143
00:18:29,040 --> 00:18:36,960
myself here, are the payback period method. It's old, it's bad, you shouldn't use it, but it's still

144
00:18:36,960 --> 00:18:49,040
out there. And then you have the two biggies, the net present value method and the other one,

145
00:18:49,040 --> 00:18:56,320
the internal rate of return method. The most popular of these is the internal rate of return method.

146
00:18:56,320 --> 00:19:16,320
It is the one that's also the weakest of all of them, of the two I should say. The net present

147
00:19:16,320 --> 00:19:22,800
value method and the internal rate of return method are mathematically and scientifically

148
00:19:22,800 --> 00:19:36,160
sound. They essentially assess where a project, the present value of a project gets below the

149
00:19:36,160 --> 00:19:46,040
point where it can't pay for the initial investment in it. Now the two different methods, and again I

150
00:19:46,040 --> 00:19:52,160
just want to make sure that you have this down, when you get a question on a quiz or an exam,

151
00:19:52,160 --> 00:19:59,480
just put the stupid numbers in. Don't think about what you're doing too much. That's all I ask of

152
00:19:59,480 --> 00:20:06,480
you is that we have Excel, we use Excel in our day and age, so we don't have to do manual calculations.

153
00:20:06,480 --> 00:20:14,800
In fact, what Excel is doing, and this spreadsheet right now, the first thing that it is doing is it

154
00:20:14,800 --> 00:20:22,120
is taking each of the free cash flows and finding its present value and then adding them up and then

155
00:20:22,120 --> 00:20:29,160
subtracting the initial investment. That's all it's doing, but the whole key is the discount rate

156
00:20:29,160 --> 00:20:37,720
that you use to do that. And like I said, valid, well what most companies use, they use their weighted

157
00:20:37,720 --> 00:20:42,520
average cost of capital. That's what they use. That's not a good idea because the weighted average

158
00:20:42,520 --> 00:20:50,560
cost of capital is essentially the measure of the risk of the entire company as an interest rate.

159
00:20:50,560 --> 00:21:00,200
Whereas a project itself might not be the same risk as the company as a whole. So you're sort of

160
00:21:00,200 --> 00:21:07,180
forcing every project to live to the expectations that the company overall has, and that might not

161
00:21:07,180 --> 00:21:13,320
be valid. A better method would be to use the capital asset pricing model. That's another method

162
00:21:13,320 --> 00:21:19,060
that you can use, but there are other methods out there too, and I won't emphasize them too much.

163
00:21:19,060 --> 00:21:24,960
I'm just going to give you a discount rate and use it, which is how it's going to be for you in your

164
00:21:24,960 --> 00:21:31,000
work, especially in the first years. If you're in corporate and you are analyzing projects, you will

165
00:21:31,000 --> 00:21:37,120
be given a discount rate. Thou shalt use this discount rate, and that's all there will be to it.

166
00:21:37,120 --> 00:21:45,000
Now the NPV, now again I emphasize, this is not, you don't bother with this. You leave it alone.

167
00:21:45,000 --> 00:21:54,600
Leave it TF alone. It is merely there to show you a comparative. Okay, I'm going to try 7% and see

168
00:21:54,600 --> 00:22:00,960
what my NPV is. That's that point on that line. Let me back this off just a little bit. That's

169
00:22:00,960 --> 00:22:11,600
that point on the line. 7% and it has an NPV of about $2,500. And then this one is just a comparison.

170
00:22:11,600 --> 00:22:21,700
What is the NPV at 12%? Well, it's negative 42, 4,300. That's that point there, and then this is the

171
00:22:21,700 --> 00:22:33,500
NPV profile line. That's, and as you can see, if I were to adjust to let's say 8%, it would plot a

172
00:22:33,500 --> 00:22:42,760
different line. That's all that's doing. So that just gives you a visuality to the exercise. Good

173
00:22:42,760 --> 00:22:54,960
news. Okay, the next thing is that the point where they crop, where the profile line crosses the

174
00:22:54,960 --> 00:23:04,080
discount rate axis, the horizontal axis, that is the internal rate of return. That's the holy grail,

175
00:23:04,080 --> 00:23:13,840
as it were, of a lot of company decision-making. It has the flaw that if the sign of the cash,

176
00:23:13,840 --> 00:23:22,440
free cash flow switches more than once, there will be multiple internal rates of return. It's

177
00:23:22,440 --> 00:23:29,960
actually, if it crosses twice, the internal rate of return, the profile line is a parabola. If it

178
00:23:29,960 --> 00:23:40,960
crosses three times, the NPV profile line is a cubic. The polynomial, the degree of the polynomial,

179
00:23:40,960 --> 00:23:49,120
the highest part of which X occurs, is the shape of the NPV profile line. You see that it crosses

180
00:23:49,120 --> 00:23:55,200
once here? So that's a linear equation. X to the first power is the highest power of X. So that's

181
00:23:55,200 --> 00:24:04,720
why that happens. That is not always how the real world works though. There are several different

182
00:24:04,720 --> 00:24:12,440
scenarios where you could get into free cash flow. For example, one classic is where you start out

183
00:24:12,440 --> 00:24:18,400
with an initial investment. You cruise along over the life of the project, but in the last year,

184
00:24:18,400 --> 00:24:26,560
you get your residual, last sell, last inventory, but your salvage value is negative because it

185
00:24:26,560 --> 00:24:33,800
costs to close it down and you're paying more to close it down than you get from the last year of

186
00:24:33,800 --> 00:24:39,920
sales. So you could have negative, then a string of positives, that's one switch, and then at the

187
00:24:39,920 --> 00:24:46,960
last year, it switches back to negative. So it's got two sign switches, which would mean that the

188
00:24:46,960 --> 00:24:53,760
NPV profile line would actually be a parabola, and that means that there are two internal rates

189
00:24:53,760 --> 00:24:59,680
of return, neither of which means anything whatsoever. They are what we call spurious

190
00:24:59,680 --> 00:25:07,840
solutions. They're spurious. So that makes the traditional internal rate of return not really

191
00:25:07,840 --> 00:25:16,680
the best way to use every time you need an internal rate of return. But let me hold that off for a

192
00:25:16,680 --> 00:25:22,800
minute. We have a way to fix it. It's not actually the best way in the world, but it's a way to fix

193
00:25:22,800 --> 00:25:29,400
it. And Excel fortunately can do that because if you have to do that by hand, it is a pain in the

194
00:25:29,400 --> 00:25:35,480
butt. It's called the modified internal rate of return. But let me go through something here. This,

195
00:25:35,480 --> 00:25:43,800
okay, this one, positive, accept, negative, reject, that's all there is to it. Its challenge is finding

196
00:25:43,800 --> 00:25:49,320
a discount rate. How do most companies do it? They cop out and say whack. They just say 7% or

197
00:25:49,320 --> 00:25:55,560
whatever their whack is. They don't use the cap M. They don't use bond plus equity premium. They

198
00:25:55,560 --> 00:26:02,720
don't do any of that. They just say whack. So it is, even at that, it's still, it is straightforward.

199
00:26:02,720 --> 00:26:09,960
Negative, if the project NPV is negative, well, you say reject. If it's positive, you say accept.

200
00:26:09,960 --> 00:26:24,320
But the internal rate of return has another way that it is used. The internal rate of return in

201
00:26:24,320 --> 00:26:34,840
a way is called the breakeven, I've even heard this term, the breakeven ROI. So for example,

202
00:26:34,840 --> 00:26:49,560
suppose that a project, well, let me show you this one here. Suppose that I say, okay, the internal

203
00:26:49,560 --> 00:27:01,720
rate of return of this project is 8.75%. See, it calculates it for you. But what if I say that we

204
00:27:01,720 --> 00:27:19,240
have a project that has an internal rate of return of, let's say, 8%. Well, 8% would be down here.

205
00:27:19,240 --> 00:27:27,800
That's a negative. So if we have an internal rate of return of a project that is unacceptable,

206
00:27:27,800 --> 00:27:35,080
we would reject it. Now here's how they use it in business. They usually use a term, and there are

207
00:27:35,080 --> 00:27:47,040
other terms for it, but they use a term called hurdle rate. This is essentially the internal

208
00:27:47,040 --> 00:27:57,240
rate of return that we will use for evaluating projects. So suppose that a company, so in other

209
00:27:57,240 --> 00:28:10,000
words, let's say that the hurdle rate is 10%. So in other words, out here at 10%, that's our

210
00:28:10,000 --> 00:28:19,960
threshold. So suppose that we do an NPV IRR and we have a project that comes in with a,

211
00:28:19,960 --> 00:28:43,280
project A has an internal rate of return of 8, let's say 8.5%. Whatever else we know or don't

212
00:28:43,280 --> 00:29:01,360
know, we know that this project A crosses the discount rate axis at 8.5%. That means that we

213
00:29:01,360 --> 00:29:11,920
would reject this project because at our hurdle rate of 10%, this is a negative NPV project. So

214
00:29:11,920 --> 00:29:19,720
the decision criterion works like this. Set your hurdle rate. Then any project that has an internal

215
00:29:19,720 --> 00:29:45,960
rate of return, project internal rate of return less than the hurdle rate, we reject because it

216
00:29:45,960 --> 00:29:53,840
doesn't meet our threshold. Any project above that hurdle rate, internal rate of return, we accept.

217
00:29:53,840 --> 00:30:03,600
That's how you do it. It's a very simple method. All you have to do is crank out the IRR of the

218
00:30:03,600 --> 00:30:09,000
project. Notice that, by the way, let me warn you of something. When you're calculating an

219
00:30:09,000 --> 00:30:17,880
internal rate of return, you don't need a discount rate. I may be repeating what I said in the last

220
00:30:17,880 --> 00:30:22,760
lecture, but I have to emphasize this. I'll give you two problems on the final exam, let's say.

221
00:30:22,760 --> 00:30:28,840
One will be find the NPV. I'll give you a free cash flow, find the NPV. Well, in order to find

222
00:30:28,840 --> 00:30:33,840
the NPV, you need the free cash flow, you need a discount rate. But then I'll give you one where

223
00:30:33,840 --> 00:30:38,640
I'll give you the free cash flow and I'll say find the internal rate of return. Don't come up and ask

224
00:30:38,640 --> 00:30:45,200
me, well, what's the discount rate? You don't need a discount rate. There's no use for it. The

225
00:30:45,200 --> 00:30:51,640
internal rate of return is the discount rate. So you don't need a discount rate if all you're

226
00:30:51,640 --> 00:30:57,800
finding is an internal rate of return. You see the temptation in this, though, is because you

227
00:30:57,800 --> 00:31:05,560
can just crank out free cash flow analysis every day and all you need to do is run internal rate

228
00:31:05,560 --> 00:31:09,800
of return. You don't need to worry about, God, what's discount rate? Just run the internal rate

229
00:31:09,800 --> 00:31:17,200
of return and compare it to your corporate policy hurdle rate. And every company that uses internal

230
00:31:17,200 --> 00:31:24,480
rate of return that I've run into has a hurdle rate. And the problem with that is kind of simple.

231
00:31:24,480 --> 00:31:33,880
Where are you getting this hurdle rate? It would have to be purely subjective. You pull it out of

232
00:31:33,880 --> 00:31:41,200
your ass. And I had, when I was consulting, I had several companies that were, you know, they were

233
00:31:41,200 --> 00:31:47,080
using internal rates of return. So they were very modern, very hip and with it. I said, well, where

234
00:31:47,080 --> 00:31:54,040
did you get this hurdle rate? I had one that had a hurdle rate on projects of 12.5%. And I said,

235
00:31:54,040 --> 00:31:59,880
well, where did that come from? And they were actually, only one person offered us an answer.

236
00:31:59,880 --> 00:32:09,040
He said, well, I know that it was, some years back, it was 12.5% when I first came here and we just

237
00:32:09,040 --> 00:32:15,160
never changed it. That's the way we always do it. But you see, that's, it doesn't take into account

238
00:32:15,160 --> 00:32:23,760
varying interest rates over time in the macro economy, the growth of the corporation, what its

239
00:32:23,760 --> 00:32:30,360
risk profile changing through time. 12.5% is actually a pretty steep, especially back in that

240
00:32:30,360 --> 00:32:37,160
time when I was doing this. That was a pretty steep, in other words, a project would really have to pay

241
00:32:37,160 --> 00:32:45,400
off big to get an internal rate of return above a 12.5% hurdle rate. In other words, the company was

242
00:32:45,400 --> 00:32:54,760
essentially biasing itself away from safe projects. See, if you had a project that came in with an

243
00:32:54,760 --> 00:33:00,720
internal rate of return of 6%, they say reject it. Well, that might be a good project. It's just a

244
00:33:00,720 --> 00:33:07,280
very safe project. Doesn't return a lot of money, but it's a very safe project. But if you find one

245
00:33:07,280 --> 00:33:13,320
that has a 20% internal rate of return, well, that's, yeah, we'll take that one any day. But

246
00:33:13,320 --> 00:33:20,560
you're also taking on a frickin boatload of risk with a project. So in other words, it was constantly

247
00:33:20,560 --> 00:33:29,200
making itself a riskier corporation because it would take only projects that were at least as

248
00:33:29,200 --> 00:33:36,480
good as 12.5%. And if the higher it was above the hurdle rate, the better they loved it. And so that

249
00:33:36,480 --> 00:33:43,000
just constantly increased the risk of the corporation because it was taking on risky projects and it was

250
00:33:43,000 --> 00:33:50,680
rejecting safe projects. Even though they would have been perfectly okay, they didn't want them

251
00:33:50,680 --> 00:33:57,120
because they did not meet that hurdle rate that the company had set. And ask the company, well,

252
00:33:57,120 --> 00:34:02,320
why did you use that hurdle rate? They couldn't tell me. They just said, that's what we do. And

253
00:34:02,320 --> 00:34:09,040
then they kind of sometimes say, well, we got this guy, he does some pretty fancy math, and this is

254
00:34:09,040 --> 00:34:14,720
what he figured out. Oh, you probably got some guy named Earl down at Earl's Bar and Grill, and he

255
00:34:14,720 --> 00:34:25,040
does financial consulting on the side. Yeah, yeah, that probably was about it. Okay, so in other words,

256
00:34:25,040 --> 00:34:31,640
this is a popular method. Internal rate of return, set the hurdle rate, reject any project that has

257
00:34:31,640 --> 00:34:39,760
an IRR below the hurdle rate, accept any project that has an IRR above the hurdle rate. Okay, so we're

258
00:34:39,760 --> 00:34:47,880
all good and dandy now, except for the fact that internal rate of return does not work if there's

259
00:34:47,880 --> 00:34:58,720
more than one flip in the sign of the cash flow. Matter of fact, you could put in a, let me show

260
00:34:58,720 --> 00:35:07,560
you something here. You could put in the numbers for a free cash flow with a negative value in one

261
00:35:07,560 --> 00:35:17,200
of them, and you know what would happen? Excel, a financial calculator, will give you an internal

262
00:35:17,200 --> 00:35:32,240
rate of return. But what it did was, okay, let me show you. Here would be a possible NPV profile

263
00:35:32,240 --> 00:35:45,000
line if you had two sign switches. It would be a parabola, degree two polynomial, two roots, in other

264
00:35:45,000 --> 00:35:52,800
words, two IRRs. Well, what Excel and a financial calculator do is they just start somewhere and

265
00:35:52,800 --> 00:35:58,560
they start searching. And let's say it starts at a low rate. Now it's doing this at the speed of

266
00:35:58,560 --> 00:36:05,400
light so you don't see how much it's doing here. But it's a, okay, we've got a negative NPV. That

267
00:36:05,400 --> 00:36:11,040
means that we are already on the wrong side. So it's going to go down and it's just going to get

268
00:36:11,040 --> 00:36:16,600
more negative. So it starts running this way and it says, bing, bing, oh, we've got a positive NPV.

269
00:36:16,600 --> 00:36:22,920
So the internal rate of return must be between here and here. And it'll just zero in on that. Like

270
00:36:22,920 --> 00:36:27,480
I said, at the speed of light, you're not seeing this happen. And then it says, here's your internal

271
00:36:27,480 --> 00:36:36,000
rate of return. If it had started somewhere like up here, it would have seen that the NPVs were

272
00:36:36,000 --> 00:36:42,040
falling and then it would have gone over here and it would have worked its way back and forth. Which

273
00:36:42,040 --> 00:36:49,440
one it would find is purely where it would start. And it would mean anything. Neither of them really

274
00:36:49,440 --> 00:36:56,880
means one damn thing. Now some books, I don't know if this one, there was a previous edition that tried

275
00:36:56,880 --> 00:37:03,880
to give some kind of a weird ass explanation. Well, this one means this. Don't, just don't. There is a

276
00:37:03,880 --> 00:37:14,320
way to modify the internal rate of return to make it so that it gives, it has only one sign switch.

277
00:37:14,320 --> 00:37:23,560
It's called the modified internal rate of return, the MIRR. And thank God we have that. Because let

278
00:37:23,560 --> 00:37:37,200
me show you, I've got an MIRR here. MIRR, okay. See this one, it's got a sign switch here, that's one.

279
00:37:37,200 --> 00:37:45,960
Then it switches, that's two. And then it switches, that's three. So in other words, this would, the NPV

280
00:37:45,960 --> 00:37:53,240
profile line would actually be a cubic equations graph. This son of a bitch would look like,

281
00:37:53,240 --> 00:38:01,600
excuse me, would look like that. Three internal rates of return. Well we can't have two, so we sure as

282
00:38:01,600 --> 00:38:07,760
heck can't have three. So you've got to figure out a way, is there a way to straighten this up? In

283
00:38:07,760 --> 00:38:18,120
other words, to go, like that. And there is. It's stupid, but it actually works in a pig's eye. It

284
00:38:18,120 --> 00:38:27,040
works on, you have to think about this. So if, see how they're at year zero and then at year three,

285
00:38:27,040 --> 00:38:35,240
you have to throw money into the project. Now obviously there would be some cost of that capital

286
00:38:35,240 --> 00:38:41,880
to do that. So we call that the financing rate. I put six percent here, you could put other things.

287
00:38:41,880 --> 00:38:48,760
But you see, on the other hand, see these years when it's making money, 15,000, 50,000, 70,000,

288
00:38:48,760 --> 00:38:56,200
10,000. That's when it's got money coming out into retained earnings that it could use for

289
00:38:56,200 --> 00:39:02,880
reinvestments, investments in other things. So in other words, in this problem there are really two

290
00:39:02,880 --> 00:39:10,480
different interest rates, discount rates as it were, or compounding rates. There is a six percent

291
00:39:10,480 --> 00:39:18,760
cost of financing. That would be a discount rate. And then there is also an interest rate, what we

292
00:39:18,760 --> 00:39:25,320
make off extra that we make in a project. Okay, we made 15 grand in the first year. Well, we can do

293
00:39:25,320 --> 00:39:32,520
something with that. So that would be a reinvestment rate of the company, whatever it can put money

294
00:39:32,520 --> 00:39:39,960
into inside the company or invest in other companies, whatever. But there will be two different

295
00:39:39,960 --> 00:39:49,680
rates. Now, here's the pain in the butt part of it if you do it by hand. First of all, you take

296
00:39:49,680 --> 00:39:57,560
anything that's negative and discount it back at the finance rate to the beginning and add it to

297
00:39:57,560 --> 00:40:07,040
the initial investment. And then you take any time that the project spits out money and you throw it

298
00:40:07,040 --> 00:40:16,040
forward as a future value to the end of the project, compounding at the investment rate. So in other

299
00:40:16,040 --> 00:40:25,560
words, what you're doing basically in this project, in this right here, is if I do these as one, two,

300
00:40:25,560 --> 00:40:37,240
three, four, five, was this a five year project? Yeah. Okay. Oh, I got to do a zero here. So there in

301
00:40:37,240 --> 00:40:46,560
year zero, there's a negative. And then there's a positive and a positive. And then a negative and

302
00:40:46,560 --> 00:40:54,040
then a positive and a positive. So what you're doing is you are discounting any negatives back

303
00:40:54,040 --> 00:41:02,120
to the present, taking a present value of them, adding them up. And it's taking any positives and

304
00:41:02,120 --> 00:41:09,640
you're finding the future value. So this one is present value at the discount rate. And all these

305
00:41:09,640 --> 00:41:20,120
that are positives, you're taking forward as future values and clustering them all up. And then you

306
00:41:20,120 --> 00:41:25,920
just zero all the numbers in between because you've done something with them. So in other words,

307
00:41:25,920 --> 00:41:31,880
what Excel is doing, what we used to do by hand, and I don't want to see, I want you to live better

308
00:41:31,880 --> 00:41:38,640
lives than I did. What we're doing, what Excel is doing is it's actually taking the present value of

309
00:41:38,640 --> 00:41:48,080
12,000, negative 12,000 and adding it to 120,000. And then it makes that 12,000 a zero. And then it's

310
00:41:48,080 --> 00:41:53,360
taking the future value at that compounding rate, the reinvestment rate, and it's taking all of

311
00:41:53,360 --> 00:41:59,520
those forward to your five. And then it's making those zeros because you've done something with

312
00:41:59,520 --> 00:42:06,800
them. And then it finds the internal rate of return of that number there at the beginning,

313
00:42:06,800 --> 00:42:15,640
a zero, a zero, a zero, a zero, and the last year right there. And it's finding the internal rate

314
00:42:15,640 --> 00:42:22,400
of return of basically a negative number at the beginning and a positive number at the end. And

315
00:42:22,400 --> 00:42:27,680
that's finding the internal rate of return of that mess. That's called a modified internal rate of

316
00:42:27,680 --> 00:42:37,200
return, MIRR. And you can do this. Let me do a, I'll do a couple of other projects. But before I

317
00:42:37,200 --> 00:42:49,240
show you that, notice that the modified internal rate of return of this project is 5.37%. Do you

318
00:42:49,240 --> 00:42:58,480
see that the financing rate is 6%? This is a project you shouldn't take because the project

319
00:42:58,480 --> 00:43:08,640
overall has a return that is less than it costs you to finance it. Let me say that again. This

320
00:43:08,640 --> 00:43:21,160
project is coming out with an overall return of 5.37%. But the capital that I needed to make this

321
00:43:21,160 --> 00:43:29,200
project happen costs me 6%. Well, that sucks. Here's a rule. It should not cost more than you

322
00:43:29,200 --> 00:43:36,360
make. That's just, it's just basically at its heart, it's just a pretty simple, stupid ass rule.

323
00:43:36,360 --> 00:43:49,640
That's all it is. So that's worth your attention. But MIRR is, is if there's more than one sign

324
00:43:49,640 --> 00:43:58,600
switch in the free cash flow, then just use MIRR. Now on a quiz or an exam, well, that's all you do

325
00:43:58,600 --> 00:44:07,920
is just put in the numbers and look at the result. Now, there are some simple problems. I think the

326
00:44:07,920 --> 00:44:12,520
book has one where the financing rate and the reinvestment rate are the same. That's kind of

327
00:44:12,520 --> 00:44:18,280
unrealistic. But you know, put, just put in whatever they say the financing rate is and what the

328
00:44:18,280 --> 00:44:25,200
reinvestment rate is and just put in the free cash flows, whatever I tell you they are, and there's

329
00:44:25,200 --> 00:44:33,680
your answer. That's all there is to it. And let me tell you again, I can't emphasize enough, that it

330
00:44:33,680 --> 00:44:41,520
is a lot easier to do it with Excel. The book uses a financial calculator, a cheapo BA2, and says,

331
00:44:41,520 --> 00:44:45,960
well, you key this here and you key that there and then you swing around a cat and you offer your

332
00:44:45,960 --> 00:44:51,720
firstborn. Just use Excel to do this. It's a lot faster. These templates, I mean, they aren't

333
00:44:51,720 --> 00:45:00,400
sophisticated at all, but it certainly is easier than doing it with financial calculators, basic

334
00:45:00,400 --> 00:45:07,400
financial calculators, and it sure is heck a lot easier than doing it manually. That's that one.

335
00:45:07,400 --> 00:45:12,920
Now let me take you over here. I forgot, I did put in, and I didn't have this in the one, so you'll

336
00:45:12,920 --> 00:45:20,160
want to download this again. Payback period method. If you want to get down to the fraction of the

337
00:45:20,160 --> 00:45:30,560
year in which you cover your initial investment, I've written a small sheet right here and you can

338
00:45:30,560 --> 00:45:37,400
extend this if you want out further. But in this project right here, you start out with an

339
00:45:37,400 --> 00:45:46,160
investment of $100 and then you make $10 in your first year, 60 in your second year, and 80 in your

340
00:45:46,160 --> 00:45:54,600
third year, maybe some more. But as you can see, if the year of crossing, it was some time before

341
00:45:54,600 --> 00:46:02,840
year three. Now you could just say simply, okay, whatever our, let's say that we have a required

342
00:46:02,840 --> 00:46:09,440
payback period of four years. Okay, we take the project because it clearly pays for itself after

343
00:46:09,440 --> 00:46:16,200
three years. Now if they want to say just exactly how much of three years, well then you have to

344
00:46:16,200 --> 00:46:23,720
work a little harder. I've got a formula here that will tell you exactly the number of years to cross

345
00:46:23,720 --> 00:46:32,120
into the payback period. In this case, the payback period, you can say three years, but if you want

346
00:46:32,120 --> 00:46:38,800
to be exact about it, it's 2.38 years. And I've got a formula right here that cranks it out for you.

347
00:46:38,800 --> 00:46:47,160
If you want to suffer, you can see that nested if statement that I wrote to do that, but there it is,

348
00:46:47,160 --> 00:46:53,000
if you need the actual exact number of years. And like I said, you can extend this, just drag the

349
00:46:53,000 --> 00:47:00,400
formula down and you can get, if it's like it doesn't pay off until year five, it'll do that

350
00:47:00,400 --> 00:47:08,600
for you too. So there you go, that's all there is to that one. So that's your payback period method.

351
00:47:08,600 --> 00:47:18,000
Now I won't get into this, I'm not going to ask you this on a quiz or a test, but when you have

352
00:47:18,000 --> 00:47:37,720
mutually exclusive projects, that can be difficult. I encountered, now technically there's an argument

353
00:47:37,720 --> 00:47:47,760
among finance people that you should never have mutually exclusive projects. There's always

354
00:47:47,760 --> 00:47:53,560
a way that you could run, if it's two good projects, you should be able to do both of them,

355
00:47:53,560 --> 00:48:03,880
if they both have strong NPVs. But there are, and I did encounter it, where at least in the

356
00:48:03,880 --> 00:48:10,720
time period in which the decision had to be made, there were two projects that were mutually

357
00:48:10,720 --> 00:48:17,520
exclusive. And I had to dig through some ancient notes of mine, because I keep forgetting how it

358
00:48:17,520 --> 00:48:23,120
worked, but this company had a very large piece of land, well it wasn't very large, it was about

359
00:48:23,120 --> 00:48:31,680
five acres of land, and there were two possible ways that they could take that land. One was for

360
00:48:31,680 --> 00:48:40,600
an industrial park, they were a business park for companies, it wasn't really high tech back in that

361
00:48:40,600 --> 00:48:46,280
time, that was in the early 90s, but they had more or less, they could put up all these office

362
00:48:46,280 --> 00:48:55,720
buildings, two floors, and they could run it that way. And then they had another possibility on their

363
00:48:55,720 --> 00:49:01,520
table, where they could take that land and they could turn it into something that was very popular

364
00:49:01,520 --> 00:49:09,920
back at the time. Now my original, I had had a memory that it was like an entertainment center,

365
00:49:09,920 --> 00:49:17,680
but it was actually, when I look back, it was a kind of mall, partly outdoor mall, but it was a

366
00:49:17,680 --> 00:49:23,160
special kind, and I've just noticed that it's kind of coming back into vogue very recently, whether

367
00:49:23,160 --> 00:49:29,360
it's going to come back full-blown, it was one of those where you have the lower level is all these

368
00:49:29,360 --> 00:49:35,360
shops and restaurants, entertainment everywhere, and then on the second and third floor it was

369
00:49:35,360 --> 00:49:43,360
upscale, what we called yuppie in the time, young upwardly mobile people, apartments with balconies

370
00:49:43,360 --> 00:49:48,880
and they could sit out there like, sort of like an Italian villa type of environment. They had a,

371
00:49:48,880 --> 00:49:55,520
they planned, you know, some restaurants and some shopping and there was even a plan for a daycare

372
00:49:55,520 --> 00:50:00,560
center in there and all this, but they could not do both with the same piece of land, so they were

373
00:50:00,560 --> 00:50:09,840
mutually exclusive projects, and that was where the question, well, which one do we use? Well the

374
00:50:09,840 --> 00:50:21,600
funniest thing was, let me show you the two NPV profile lines of these. One of them had an NPV

375
00:50:21,600 --> 00:50:29,800
profile line that looked something like this. The other one had an NPV profile line that, well,

376
00:50:29,800 --> 00:50:42,520
that's a little too steep, but it had a much steeper NPV profile line, like that. See, the

377
00:50:42,520 --> 00:50:51,160
problem was that they had different internal rates of return. This was project A and this was project

378
00:50:51,160 --> 00:51:01,360
B. Project B had a lower internal rate of return than project A, but at low discount rates it had a

379
00:51:01,360 --> 00:51:15,240
higher NPV. See how project B had discount rates down in here, it had that NPV, whereas project A

380
00:51:15,240 --> 00:51:25,800
had that NPV. So at low discount rates for fighting the NPV, you'd say accept project B, but at high

381
00:51:25,800 --> 00:51:33,360
discount rates, like up in here, this one would actually have a negative NPV. B would have a

382
00:51:33,360 --> 00:51:41,640
negative NPV. So the whole question was, it came down to, well, we've got to choose a discount rate.

383
00:51:41,640 --> 00:51:51,480
Now, the trick here is to find the crossover rate, because it's a crossover rate. Any discount rate

384
00:51:51,480 --> 00:51:59,920
you would use below the crossover rate, you'd take B. Any discount rate above the crossover rate,

385
00:51:59,920 --> 00:52:07,880
you would take A. And so it would just boil down to, well, what are we going to use for our discount

386
00:52:07,880 --> 00:52:13,840
rate? And they said, well, why don't we use a hurdle rate? And the problem was that their hurdle

387
00:52:13,840 --> 00:52:22,080
rate was lower than the IRR of either of them. So with the hurdle rate, you'd take them both,

388
00:52:22,080 --> 00:52:27,560
but you couldn't take them both. See, if I had a hurdle rate down here somewhere, you'd take both

389
00:52:27,560 --> 00:52:34,920
of them because they both exceed their internal rates of return, exceed the hurdle rate. And their

390
00:52:34,920 --> 00:52:39,880
hurdle rate was actually fairly low. And so they said, by the hurdle rate, internal rate of return

391
00:52:39,880 --> 00:52:49,000
method, we take them both. And so it all boils down to the crossover rate. Now, I will not ask you to

392
00:52:49,000 --> 00:52:55,240
find a crossover rate. I'm bringing it up here because it does happen from time to time. You have

393
00:52:55,240 --> 00:53:03,800
two projects and you just can't do both of them because of some constraint on you. Oftentimes,

394
00:53:03,800 --> 00:53:11,520
that constraint is land. Land you don't have access to. And that was the case with the convention

395
00:53:11,520 --> 00:53:17,600
center in downtown Bloomington. They had one piece of land and they had to decide what to do with it.

396
00:53:17,600 --> 00:53:22,440
There were several different things they could have done. For one thing, they could have sold it.

397
00:53:22,440 --> 00:53:28,880
They could have made this convention center, which is what they did, or they could have made it into

398
00:53:28,880 --> 00:53:37,440
some kind of a community entertainment center. A lot of different things, some of it's kind of related.

399
00:53:37,440 --> 00:53:46,200
But they did not even consider mutually exclusive projects. They were hell-bent on one. And if they

400
00:53:46,200 --> 00:53:51,880
had considered other projects, they probably would have, and also been more realistic in their

401
00:53:51,880 --> 00:53:57,360
assessments of future expected free cash flows, they probably would have taken something else.

402
00:53:57,360 --> 00:54:04,600
So it's worth it to say, what else could we do? You don't obsess with it, but you ask, are there

403
00:54:04,600 --> 00:54:11,800
other possibly profitable things you can do? This mostly happens in real estate, where you can decide,

404
00:54:11,800 --> 00:54:23,360
okay, a residential apartment complex or something commercial. That's a big one for a lot of this

405
00:54:23,360 --> 00:54:30,800
mutually exclusive decision making. A strip mall versus an indoor mall, things like that.

406
00:54:30,800 --> 00:54:42,720
That's where this comes in. Now, one last one that I will bring up. It's the simplest one in the world

407
00:54:42,720 --> 00:54:52,440
to do. And almost any business person who's an entrepreneur is going to do this if he possibly

408
00:54:52,440 --> 00:55:03,720
can. It's very straightforward. And I do it. And I even have my numbers to show you what it means.

409
00:55:03,720 --> 00:55:13,480
It's called breakeven. Breakeven is simple. It just works like this. Look, your profit is going to be

410
00:55:13,480 --> 00:55:24,760
your revenue minus your costs. And you're going to say, I'm in college for a degree and I already

411
00:55:24,760 --> 00:55:32,920
knew this. What are you getting at? Very simple idea. Now, the costs actually have two parts.

412
00:55:32,920 --> 00:55:41,280
There are the variable costs and there's a fixed cost. Now, the variable cost moves with your output,

413
00:55:41,280 --> 00:55:51,560
moves with your sales. My variable costs. So, give you an example. In my business, the average,

414
00:55:51,560 --> 00:56:00,920
I make and sell art. Photographs, paintings, that kind of stuff. Okay, so I have to get that ready for a show.

415
00:56:00,920 --> 00:56:11,440
Okay, so at the show, I'm going to have the cost of the frame, the dry mount board, the dust backing,

416
00:56:11,440 --> 00:56:19,400
the museum glass, the wire, and all that. Put that together, that runs approximately, if I do it with good

417
00:56:19,400 --> 00:56:41,280
quality stuff, $225 per unit of art. So, in other words, my unit variable cost is that. But I also have fixed cost,

418
00:56:41,280 --> 00:56:48,680
the cost of the exhibition fee. Sometimes it's not bad, sometimes it's a killer. I also have the fixed cost,

419
00:56:48,680 --> 00:56:55,320
whether I sell anything or not, these are going to be there. They're fixed. I have the cost of driving to the

420
00:56:55,320 --> 00:57:03,240
show and driving back. And I have the cost of my infrastructure, my pop-up tent, my wire, my frames,

421
00:57:03,240 --> 00:57:11,040
and all that kind of stuff. And that fixed cost on a seasonal divided by the number of shows that I do runs

422
00:57:11,040 --> 00:57:19,440
about $2,000. And that adds in, that's including an estimate of my booth fee, what they call the booth fee,

423
00:57:19,440 --> 00:57:30,600
the exhibition fee, and all that kind of stuff. So that's a fixed cost. And finally, I have my price of my art,

424
00:57:30,600 --> 00:57:44,360
unit price. And that I average about $800 per artwork on average. We got all the pieces. So in other words,

425
00:57:44,360 --> 00:57:59,440
my profit boils down to a simple, the price, unit price times the quantity minus these two, which would be

426
00:57:59,440 --> 00:58:12,800
$225. Well, let me just put it this way, a little v times the output plus the fixed cost. Doing a little bit of

427
00:58:12,800 --> 00:58:29,320
rearranging p times q minus little v times q minus fc. And that's my profit. Now, I want to factor out the q on

428
00:58:29,320 --> 00:58:48,440
the first part. P minus v times q minus fc. First things first, if you look carefully, that is nothing but a

429
00:58:48,440 --> 00:58:57,640
y equals mx plus b's y. The x, the independent variable, is a q. The y is the profit. P minus v is the slope.

430
00:58:57,640 --> 00:59:06,880
And negative fc is the y-intercept. It's just the y equals mx plus b line. So in other words, if I were to graph

431
00:59:06,880 --> 00:59:26,640
this, q here, profit here, it looks like that. The y-intercept is negative fc, and the slope is little v minus p,

432
00:59:26,640 --> 00:59:39,440
p minus little v. A little side note here. In common business terminology, we call that price minus unit variable

433
00:59:39,440 --> 00:59:45,600
cost, unit price minus unit variable cost, we call that profit, we call that our margin, our unit margin. It's just

434
00:59:45,600 --> 00:59:51,600
the way, it's just a term. Technically, margins are supposed to be part of ratio and all, but the common lingo is

435
00:59:51,600 --> 01:00:17,600
my unit margin is p minus v. So my unit margin here is unit margin, where the hell is 800, $575. That's my unit margin.

436
01:00:17,600 --> 01:00:35,600
Now, our big question is, okay, where do I break even? Quantity break even. Okay? You follow it? That's all there is to it.

437
01:00:35,600 --> 01:00:45,600
I need to know that. I really, really care about that. And every business does care about how many it has to sell to make a

438
01:00:45,600 --> 01:00:55,600
profit. So in other words, we want the zero point of profit, which would be p minus v, the unit margin, times the

439
01:00:55,600 --> 01:01:06,600
break even quantity minus the fixed cost. That is what we're after. So in this, you rearrange it a little bit, and the

440
01:01:06,600 --> 01:01:19,600
survey says that your quantity break even, adding fc to both sides and dividing by the p minus v, is fixed cost over unit

441
01:01:19,600 --> 01:01:32,600
margin. That's all there is to it. It's simple. And as you can see, the worse your fixed costs are, the higher your break even.

442
01:01:32,600 --> 01:01:42,600
The better your spread between unit price and unit variable cost, the lower your break even. And this, all you have to do in

443
01:01:42,600 --> 01:01:53,600
this one is put in your numbers. Now, let me do this. Let's say that I have, I'm going to put in my unit price is $800. My unit

444
01:01:53,600 --> 01:02:10,600
variable cost is $225. My unit fixed cost is $2,000. So I have to make, I have to sell six. I have to sell six. Now let me

445
01:02:10,600 --> 01:02:20,600
point something out. Suppose that I can up my unit price to let's say $875 if it's a show up in Schomburg or some place like

446
01:02:20,600 --> 01:02:41,600
that. $875, what, is this B? Oh, I screwed up there, you're right. Let me get that out. I screwed that up. Okay, so I put in, let

447
01:02:41,600 --> 01:03:00,600
me put in my numbers again there. The $875, the unit variable is $225 and my fixed cost is $2,000. I knew that was not going to

448
01:03:00,600 --> 01:03:13,600
be real. 3.08 units. Okay, so if I say how many do I have to sell to break even? Four. Don't say 3.08. I can't break off a piece.

449
01:03:13,600 --> 01:03:27,600
Here's your damn sale. No, it's the first units above the zero point. So whatever fraction there is, you just round it up.

450
01:03:27,600 --> 01:03:37,600
Because if I round it down, I lose. So you round up to say that's break even. So in my case, four to show. And that sounds easy,

451
01:03:37,600 --> 01:03:48,600
that is hard as hell in my business. But yeah, this is how it's done. And it's a very simple, but every good business, especially

452
01:03:48,600 --> 01:03:57,600
if it's small, it has to say this is what we have to do in order to stay in business. Because if we don't do that, then we haven't

453
01:03:57,600 --> 01:04:08,600
covered our business expenses, fixed and variable. It's a very simple and all you have to do is put the numbers in there and

454
01:04:08,600 --> 01:04:18,600
you're all done. Okay, that's all I have for you today. I thank you.

